As continuation of FSIW Stage 1, BYME has been awarded for FSIW Stage 2 to deliver the improvement works on emergency lighting system, sprinkler system and Ventilation & Air Conditioning (VAC) at the Grandstand I and Grandstand II.
Major challenges for this project are to identify existing deficiency of various FSI system by extensive site survey and to carry out the physical installation without system interruption and disruption of operation for HKJC during on-season period.
As such experienced project team has been deployed on site to establish well-planned working schedule and to arrange proper housekeeping during the operation/installation within Sha Tin Racecourse.
Scope of works
- Improvement work on sprinkler system
- Improvement and examination work of essential lighting
- Improvement and examination work of Ventilation and Air-conditioning system (VAC)
- Lift modernization