Milestone for Tseung Kwan O Fire Station and Accommodation Project

We are pleased to share that Tseung Kwan O Fire Station-cum-ambulance Depot with Departmental Quarters and Fire Services Accommodation project has reached a milestone with the successful mockup inspection.

This project has utilized Modular Integrated Construction (MiC) techniques to construct over 600 modules. And BYME is responsible for the Building Services installations which include Mechanical Ventilation & Air-conditioning, fire services, electrical, plumbing & drainage and more. The recent mockup inspection was attended by government officials, project consultants, and other key stakeholders.

Mass production of modules will begin and the project shall proceed with site installation in Q1 of 2024.

“We are proud to be part of this MiC project. It demonstrated our capability to embrace innovative technology while striving to provide high-quality and efficient services.” Billy Lo, Project Manager expressed.