To keep up with the momentum of Hong Kong’s economy boom, Swire Properties continued their spearheading effort to be the biggest player in the market by constantly developing new properties.
Built on the foundation of their success with Cityplaza One and Two, the construction of Cityplaza Three and Four was undertaken by Dragages et Travaux Publics together with its E&M arm BYME.
BYME successfully delivered the complete E&M package accommodating two 23-storey grade-A office towers sharing a common basement.
Environmentally-friendly cooling plant
Scope of works
Design, supply, installation and Testing & Commissioning (T&C) of all Electrical & Mechanical (E&M) services for two 23-storey grade-A office towers which comprised a sea-water cooling plant at basement.
- MVAC (sea-water cooling system)
- Electrical and Extra Low Voltage (ELV) system
- Fire services (FS)
- Plumbing & Drainage (P&D)