Contract 8235 – Miscellaneous Enhanced Works for West Kowloon

July 2019 - December 2019

E&M works for Room Q1, PC5, Q25A & S8:

  • New install 4 nos. of fan coil and associated pipework in Q1, PC5 and S8
  • 25 nos. down light in S8
  • Dismantle 4 nos. CRAC and replace 4 nos. fan coil and associated pipework.
  • Dismantle and relocate 1 no. cold water pipe at Q25A

ABWF works for Room Q1, PC5, Q25A & S8

  • To modify and make good ceiling at Q1, PC5, Q25A after completion of fan coil installation.

New install wall padding for 5 Nos. Room at HKCIQ area.




Scope of works

Supply and installation of the following services to Western Kowloon Terminus:

  • ABWF,
  • Mechanical Ventilation & Air Conditioning, (MVAC)
  • Electrical Service Systems
  • Plumbing and Drainage System (P&D)
Client MTR Corporation Ltd.
Location Express Rail Link(XRL) / West Kowloon Terminus(WKT)
Main Contractor BYME Engineering (HK) Ltd.
Architect Aedas Ltd.
Consultant Meinhadt (HK) Ltd.
Year July 2019 - December 2019