Digital Realty Data Centre Phase 2

Apr - Sep 2014

BYME was awarded as the Main Contractor encapsulating a turn-key package .

This fast-track project consists of the construction of two 1,000 sqm of data hall suites and their associated plant rooms in the existing 18,000 sqm brownfield data center facility owned by the client. The existing data center facility has numerous telecommunication and power cable landing facilities, making it an ideal location for data center facilities. Upon the completion of the construction process, the data hall suites were certified Tier III by the Uptime Institute through rigorous testing scenarios. 




Scope of works

Supply, Installation and Testing & Commissioning (T&C) of all Electrical & Mechanical (E&M) Services, Builders Works, and Fit Out Works to achieve Tier III data hall certification.

Builders Works

  • Raised-floor system
  • Structural openings, kerbs, and plinths
  • Painting and finishes
  • Floor, wall, and ceiling works
  • Steel gantry at roof

Electrical and Extra Low Voltage (ELV) Systems

Air Conditioning and Mechanical Ventilation Systems (ACMV)

Fire Services (FS)

Plumbing and Drainage Services (P&D)

Client Digital Savvis Investment Management Ltd.
Location Tseung Kwan O, New Territories, Hong Kong S.A.R.
Main Contractor BYME Engineering (HK) Ltd.
Architect Studio One Design Ltd.
Consultant DSCO Group Ltd.
Year Apr - Sep 2014