In succession to completion of Phase 2, this project is the Phase 3 of the HKG10 datacenter of Digital Realty (DLR)
The project consists of the construction of two datahall suites (5.2MW total IT load).
BYME was awarded the role of Main Contractor again for management services, coordination services, installation and T&C services of the M&E equipment, structural modification services, and builder’s works services.
The key challenge of this project is the management of the various long-lead equipment procured directly by the client, namely: water-cooled chillers, packaged generator sets, packaged pump rooms, uninterruptible power supply units, HV/LV transformers, HV switchgears, LV switchboards, and computer room air handlers.
Scope of works
Supply, installation and Testing and Commissioning (T&C) of all Electrical & Mechanical (E&M) Services, builders works, and fit out works to construct a UptimeInstituteTierIIIcertified, purpose built data centre
Builders Works
- Raised-floor System
- Structural Openings,
- Painting and Finishes
- Floor, Wall, and Ceiling Works
- Steel Gantry at Roof
Electrical and Extra Low Voltage Systems (ELV)
Air Conditioning and Mechanical Ventilation Systems (ACMV)
Fire Services (FS)
Plumbing and Drainage Services (P&D)