The works included within this contract are located primarily in the West Kowloon Terminus of the Express Rail Link between Hong Kong S.A.R. and mainland China.
The approximate total floor area within the scope of this works is 45,050m2 covering 726 individual spaces.
The biggest challenge of this contract is the re-designing and re-routing of the fire services and plumbing & drainage systems to be installed to suit to the other services that had been installed on site.
Scope of works
Supply and installation of Fire Services and Plumbing & Drainage packages for Mainland Customs, Immigration and Quarantine Facilities (MCIQ) inside West Kowloon Terminus of the Express Rail Link:
Wet Fire System (FS)
- Main works in Basement 2 and 3
- Minor works in Basement 1 and 4
Plumbing & Drainage System (P&D)
- Pump: 4 sets
- Pressure Vessel: 2 no.
- FG Tank
- Hot Water System
- Non-Potable Water System
- Potable Water System
- Soil and Waste Drainage System
- Sanitary Fittings Connections