The project aims to improve the indoor air environment and passengers’ comfort level in Hong Kong International Airport. The Airport Authority Hong Kong initiated the replacement of the existing Pre-Conditioned Air equipment serving the Aircraft Loading Bridges (ALBs) of Terminal.
To avoid disrupting the terminal’s operation, detailed planning of work sequences was the key to the successful delivery of this project.
Scope of works
Supply, installation, Testing & Commissioning (T&C) of the following systems without disruption of the operation of the terminal:
- 48 sets of pre-conditioned air equipment serving Aircraft Loading Bridges (ALBs)
- Diverter assemblies