The project consists of a full renovation of a 71,000m2 GFA five-star hotel housing 503 guest rooms in Central district.
BYME was tasked to provide the turn-key E&M systems for the entire renovation.
Notable challenges include the completion of the main risers serving the entire building to pave the way for the grand opening of lower building floors and upper building floors, while carrying on with the works on the middle building floors.
The keys to the success of this project were the implementation of innovative pre-fabricated system approach, timely relocation of the E&M services within the risers to suit the new requirements, and efficient Just-In-Time logistic control for the delivery of the materials and equipment to the heart of this city.
Scope of works
Design, supply, installation, demolition, removal, modification, Testing & Commissioning (T&C) and maintenance of the main Electrical & Mechanical (E&M) services:
- Decommissioning of the unused E&M systems
- Supply, Installation, and T&C of E&M services serving the 503 guestrooms, restaurant, spa facilities, retail shops and other front of house areas and back of house plant rooms
- Replacement of the existing Generator Set, Boiler Plants, Circulation Pumps, Air Handling Units, Primary Air Handling Units, and other equipment
- Integration of the newly-installed systems into the existing systems